 |
|

10/14/07, 05:06 AM
|
 |
|
|
Join Date: May 2002
Location: The Ozarks
Posts: 5,201
|
|
|
Running electric down driveway?
We just came back from meeting with a contractor to intall a 1/4 mile road/driveway onto our land. We've decided to go ahead and run electricity into the property, however we don't want any lines/easements on our land.
My husband is going to consult with a couple of the electrical engineers at the nuke plant where he works on running electric underground for that distance, so we use the right stuff.
We're wondering though, on burying it along the drive, in PVC pipe while the road is being put in. Any suggestions on a good way to do this, to avoid it being crushed or pushed over?
The electric company won't discuss running power for that distance underground, (even at our expense) so if we install a meter at the road, we figure we can just have them hook up to it and avoid the discussion.
|

10/14/07, 05:37 AM
|
 |
|
|
Join Date: Feb 2007
Location: Maine
Posts: 259
|
|
|
When running a line that long you might need a transformer at your house instead of 1/4 mile away. Something you may want to consider. It will be substaintially cheaper letting the power company run the line and put a transformer to your house. I just had a similar situation on my place in Maine.
__________________
"Knowledge didn't hatch out on a flat rock." Clayton Peary
|

10/14/07, 05:44 AM
|
 |
|
|
Join Date: May 2002
Location: The Ozarks
Posts: 5,201
|
|
|
We'll research the necessary cabling/transformer etc, but the utility company won't run power underground for more than 150' (at our expense) much less 1/4 mile.
|

10/14/07, 05:48 AM
|
|
|
|
Join Date: Sep 2003
Location: Whiskey Flats(Ft. Worth) , Tx
Posts: 8,749
|
|
|
...............I think the problem you will encounter from the electric company is that they will not allow you to effectively connect onto their 7200 volt supply line and then run that voltage over YOUR wires . This is why they will require that you provide them with a ROW as without such they can't legally work on Your poles or your wires . And , your nor your husband will be willing to climb the poles and fix the problems should you have any . Probably be better to set up a solar system with good diesel generator . , fordy
|

10/14/07, 06:13 AM
|
 |
In Remembrance
|
|
Join Date: Sep 2006
Location: SW Mo.
Posts: 1,625
|
|
|
The farthest part of your electrical system must be within 300 ft of the transformer. Otherwise there is significant voltage loss. So if the electric company will not run underground to the transformer then you are stuck with overhead wires and a right of way or create your own. You might run the overhead next to the road to get part of the necessary clearance. Welcome to the world of creating your own place.
|

10/14/07, 06:54 AM
|
 |
|
|
Join Date: Sep 2005
Location: Ohio
Posts: 19,350
|
|
|
I don't know how it works where you live but here the electric company is responsible for everything up to and including the meter. Grandma has a pole with a transformer in front of her house, nearly 1/4 mile lane, and when the transformer went out, she didn't get charged one cent for it's replacement.
Underground lines just aren't an option because the electric companies here won't do them.
|

10/14/07, 07:13 AM
|
 |
|
|
Join Date: Jul 2004
Location: Jones Co, Texas
Posts: 676
|
|
|
Actually, your electric company, _might_ let you install your own duct bank, and put a pad mount transformer at your house... or rather, let an electrical contractor put it in. Did two jobs like that when I was still in dirt work. The property owner contracted the ductbank.
Unless you are quite rich, I doubt you'll be able to afford that. Ductbank for 7200V for would be 1/4mile of 4" pvc pipe, 1/4 mile of very expensive wire, enough concrete to give 3" of cover on all sides of the pipe for 1/4 mile, and of course digging and backfilling 1/4 of ditch. Even if you were running only about 300 feet yourself of 240v, the wire alone for 300 feet would well over $2000 with the way copper prices are, let alone ductbank and wires suitable for 7200V for 1/4 mile.
I agree with the other poster about having the electric company do some overhead work up to a point, then perhaps going underground once you are close enough to the house. My electric company will do overhead for free up to a 1/4 mile.
Four years ago I did about what you want to do, but at only 200 feet. I used direct burial wire, did ALL the work myself, and still spent about $2500 by the time I rented the backhoe, bought the wire, the meter base, the panels, etc.
|

10/14/07, 07:19 AM
|
|
|
|
Join Date: Jan 2007
Posts: 3,037
|
|
|
You are going to have to go underground primary with a transformer and meter at your house. I personally can't see how an electric utility provider will allow you (even if you buy the wire, transformer and install to their specs) to connect a privately owned primary service to their service. You also might be aware that without a R-O-W easement you are responsible for all maintenance and VERY FEW licensed electricians are licensed to work on primary electric. 6-10 KV is not something the average homeowner can troubleshoot and repair.....that stuff has a 10 foot clearance (meaning if you are within 10 feet of an open energized conducter you are in the strike zone). If you are dead set on no easements, go with an alternative energy source and no landline phones.
|

10/14/07, 08:24 AM
|
 |
|
|
Join Date: May 2002
Location: The Ozarks
Posts: 5,201
|
|
|
We haven't had a land line phone in years. We had planned to go off the grid, but aren't sure it isn't going to be just as expensive. The well is probably the biggest issue. We have little wind, and our well will likely be around 400', average for the area.
|

10/14/07, 09:14 AM
|
 |
Offgridkindaguy
|
|
Join Date: Feb 2004
Location: Out in the Boonies.. In Ohio
Posts: 790
|
|
|
I would take a good, long look at the alternatives. Seems that many folks have had the same issue with the costs of getting the grid to the house. That's what made my decision..
As for the well, design for water storage at ground level either in a cistern or some sort of tank. A 15KW generator and a standard submersible pump can get the water out of the well with ease. After that, It can be pressurized via low voltage/low wattage pumps..
My phone company gave me a drop on a pole that was on the border of my property. I ran almost 1/2 mile of wire from the house to that pole and made connection. I am responsible for the run that I installed to the conection point at the pole..
Off grid and frugal goes hand in hand. If you plan to operate large machinery, the grid is the way to go.
~Don
__________________
Diogenes' Philosophy..
"The gods gave man an easy life, but man has complicated it by itching for luxuries."
|

10/14/07, 09:40 AM
|
|
|
|
Join Date: Jan 2006
Posts: 171
|
|
|
Actually, you don't need to run anything through a duct. The underground cable they use now for primary is already self-contained in a bendable plastic tube. All that needs to be done is for it to be laid in a four foot ditch padded with screening. The actually putting in of the cable, should only take a half hour for a 1/4 mile run. Then you fire up your rent-a-hoe and cover everything up. On your end, you'll have a pad-mount transformer with secondaries running from that to your home. On the other, a riser going up the pole and tapping onto the primary at the street. This is a two day job.
Find a lineman, offer cash under the table and things might happen lol.
|

10/14/07, 09:45 AM
|
 |
|
|
Join Date: Apr 2006
Location: Western Washington
Posts: 2,400
|
|
|
If you stick with underground you need to find out from people in the area what causes problems. I've heard of several neighborhoods that have had problems with the underground for the first few years due to ground settling. I've also heard of tree roots causing problems or ground water.
The power company may or may not be the one that has to fix the lines if there is a problem before the house. People found out the hard way that not all the outside stuff for the power was the power companies responsibility.
__________________
Give Blood it saves lives.
|

10/14/07, 09:57 AM
|
|
|
Quote:
|
Originally Posted by CJ
We haven't had a land line phone in years. We had planned to go off the grid, but aren't sure it isn't going to be just as expensive. The well is probably the biggest issue. We have little wind, and our well will likely be around 400', average for the area.
|
Off grid installation would be more expensive, but by the time you pay to have all that service run from a 1/4 mile away for on grid, you would have paid a purty good chunk of money that could have been used for solar/wind power.
However, I think that a combination of both grid, solar, and wind power is the ideal setup. Most likely if the sun ain't shinning then the wind will be blowing. Today I have both. So if I was set up right, I would probably be selling some power back to the electric company.
|

10/14/07, 10:04 AM
|
|
|
|
Join Date: Jan 2007
Posts: 3,192
|
|
|
When we put our electric in (2004), we didn't want poles either. The total run of the wire was right at 500', We put in the breaker box and left wires for them to hook up. They trenched the line, installed the transformer, ran the lines and billed us $650. They still have responsibility for everything from the meter out, so they can still come on your property. For a 1/4 mile stretch, you'd be talking BIG bucks. I'd probably run poles. They won't be on the easement much anyway. Before we got the "smart" meters that signal the usage out, they drove in once a month to read the meter anyway.
|

10/14/07, 10:32 AM
|
|
|
|
Join Date: May 2003
Location: Zone 7
Posts: 10,559
|
|
|
I doubt that you will be able to accomplish what you are wanting to achieve. However, you do not want the line under the roadbed. You will want the burial to be parallel to the road and a few feet to on side. This will keep the traffic from loading the wire with the over burden and possible pushing a stone into the wire. I have a similar setup for my power coming in and I have a run that is around 1400 feet however I have a transformer centrally located near the house and the main outbuildings. From the transformer power is then delivered to two main panels. The power company reads the meter remotely and I have no problem with the right of way. The power company also has responsibility for the maintenance all the way in to the meter. My obligation starts at the delivery side of the meter thus I am relieved of a lot of risk should the supply from the main fail. This is not much of a compromise IMO.
__________________
Agmantoo
If they can do it,
you know you can!
Last edited by agmantoo; 10/14/07 at 10:37 AM.
|

10/14/07, 11:19 AM
|
|
|
|
Join Date: Jan 2003
Location: WV
Posts: 529
|
|
|
Let the electric company run poles to within 150 feet of the house then go underground with the rest.
After it's in you probably won't see them on your property again.
__________________
HIGHGROUND
|

10/14/07, 12:15 PM
|
 |
Moderator
|
|
Join Date: Jul 2004
Location: Mountains of Vermont, Zone 3
Posts: 8,878
|
|
When we bought our place the previous owner had just spent $15,000 putting in electricity. It was one mile of poles. That was $15,000 in 1985 so multiply it by 5 or 10 now. My brother just looked into putting in grid tie in for 1/3rd mile and the utility company wants $45,000 (two years ago) and my brother is responsible for putting in the trench and then covering it. The utility just lays the cable in the trench and connects it to the transformer and meter.
For that same money I could put in the fanciest solar electric system and be off grid. I would suggest generating your own power. The key is to start by reducing your needs as low as possible so the system won't cost too much. It may then turn out to be cheaper than hooking up to the grid. After that every month you'll be saving more money by not paying for utility electric.
Cheers
-Walter
Sugar Mountain Farm
in the mountains of Vermont
http://SugarMtnFarm.com/blog/
http://HollyGraphicArt.com/
http://NoNAIS.org
__________________
SugarMtnFarm.com -- Pastured Pigs, Poultry, Sheep, Dogs and Kids
|

10/14/07, 12:41 PM
|
 |
|
|
Join Date: May 2002
Location: The Ozarks
Posts: 5,201
|
|
|
Wow, lots of different opinions and experiences here. I guess we need to speak with the electric company more.
Running it above ground isn't a big deal, it won't cost much at all to do that, they'll pay for most of it. However, we just don't want the poles/easement on the land, it's so unsightly to look at it where they clear all the trees, plus then we run the risk of them branching off of that easement if someone else needs access, and we're the closest access point.
We'd be willing to spend $20k or so on an offgrid setup, if it would adequately supply our needs. What we don't want to do is spend a chunk on the system, only to have to supplement it with a bunch of propane plus fuel for a genset.
When we have to run our RV off the genset, it costs us around $30 a day, plus our propane use.
|

10/14/07, 12:47 PM
|
 |
|
|
Join Date: May 2002
Posts: 7,692
|
|
|
If its like it is around here, the electric company just wont provide service unless you sign an easement. That simple. And if somebody then past your place wants electric, they have the right to run lines through your land anywhere they want. Dont like the way they do buisiness, then produce your own power. Which isnt bad idea anymore as fast as energy prices are rising. Over last couple years my electric bill has doubled and not from me using more electricity.
__________________
"What would you do with a brain if you had one?" -Dorothy
"Well, then ignore what I have to say and go with what works for you." -Eliot Coleman
|

10/14/07, 12:58 PM
|
 |
|
|
Join Date: Oct 2003
Location: Carthage, Texas
Posts: 12,261
|
|
They "Can" run the line underground for a quarter mile... whether they'd do it, is another question. They would require an easement. The housing development bordering my place has a primary pole/wire line around the perimeter of the development, and underground wires down all of the side roads, some as long as 3/4 mile.
The easement shouldn't be a problem, if the wires are underground... they can be laid in the side ditches. If you're worried about neighbors hooking on, and creating a 'development zone'  , make sure you're lines are a certain distance away from property boundaries.
Underground lines are more expensive than poles/wires, but if you had to clear out a lot of rugged terrain's timber/brush, it might equalize out.... also aesthetics have a certain value. I wish that I'd had underground wires the last 1/4 mile to my house...
Running your own lines underground from a transformer a 1/4 mile would probably cost more than your land... and the power losses would be horrendous. Really not feasible.
__________________
Luck is what happens when preparation meets opportunity. Seneca
Learning is not compulsory... neither is survival. W. Edwards Deming
|
| Thread Tools |
|
|
| Rate This Thread |
|
|
Posting Rules
|
You may not post new threads
You may not post replies
You may not post attachments
You may not edit your posts
HTML code is Off
|
|
|
All times are GMT -5. The time now is 03:05 AM.
|
|