
12/01/05, 08:15 PM
|
|
|
|
Join Date: Sep 2003
Location: Whiskey Flats(Ft. Worth) , Tx
Posts: 8,749
|
|
Quote:
|
Originally Posted by SouthernThunder
Thanks fordy. Sounds like a plan. 
|
............One other point.....Once they had all their concrete forms up and the beams dug the builder had the concrete guy pour a 4 sided protective wall around the plenum with 1 piece of each of the PVC runs projected Thru the protective wall and hooked to the plenum . This way when they actually poured the slab the weight of the concrete would NOT displace the plenum from it's designated position . Then , after the protective wall cured they finished running the PVC ducts and then they were able to tie all their steel as the PVC was set deep enough that only the vertical portions of the ducts were sticking up above grade . I've never seen anyone do this but it works very well . ..fordy...
|